Monday, January 27, 2020
Change log?
A comprehensive list of changes submitted during the project and their current status.
Friday, January 24, 2020
What are the Project documents?
Project documents:
1. Activity attributes
2. Activity
list
3. Assumption
log
4. Basis of
estimates
5. Change log
6. Cost
estimates
7. Cost
forecasts
8. Duration
estimates
9. Issue log
10. Lessons learned
register
11. Milestone
list
12. Physical resource
assignments
13. Project
calendars
14. Project
communications
15. Project
schedule
16. Project schedule
network diagram
17. Project scope
statement
|
18. Project team
assignments
19. Quality control
measurements
20. Quality metrics
21. Quality report
22. Requirements
documentation
23. Requirements
traceability matrix
24. Resource breakdown
structure
25. Resource calendars
26. Resource
requirements
27. Risk register
28. Risk report
29. Schedule data
30. Schedule forecasts
31. Stakeholder
register
32. Team charter
33. Test and
evaluation documents
|
What is Project Charter?
- It is a written document issued by the project iniciator or sponsor.
- It authorizes/approves the existance of a project.
- It also provides the project manager with the authority to apply organizational resources to project activities.
- It contains the high level information of the project, such as objective, product, service ect.
- The project releted information will be written in brief.
The main parts are as followings:
1. Key stakeholder list
2. Preapproved financial resources.
3. Overall project risk.
4. Project approval requirments.
5. Project exit criteria.
6. Assigner project manager responsibility and authority level.
7. Name and authority of project sponsors.
8. Summary mileston schedule.
PMP Knowledge areas.
1. Integration Managenent
2. Scope Managenent
3. Schedule Managenent
4. Cost Managenent
5. Quality Managenent
6. Resource Managenent
7. Communicatio Managenent
8. Risk Managenent
9. Stakeholder Managenent
2. Scope Managenent
3. Schedule Managenent
4. Cost Managenent
5. Quality Managenent
6. Resource Managenent
7. Communicatio Managenent
8. Risk Managenent
9. Stakeholder Managenent
Thursday, January 9, 2020
Why Should A Steam Or Moisture Separator Be Installed In The Steam Line Next To A Steam Turbine?
All
multistage turbines, low-pressure turbines, and turbines operating at
high pressure with saturated steam should have a moisture separator in
order to prevent rapid blade wear from water erosion.
Thursday, January 2, 2020
What Is Meant By Critical Speed?
- It is the speed at which the machine vibrates most violently.
- It is due to
many causes, such as imbalance or harmonic vibrations set up by the
entire machine.
- To minimize damage, the turbine should be hurried through the known critical speed as rapidly as possible. (Caution, be sure the vibration is caused by critical speed and not by some other trouble).
What Are Four Types Of Turbine Seals?
- Carbon rings fitted in segments around the shaft and held together by garter or retainer springs.
- Labyrinth mated with shaft serration’s or shaft seal strips.
- Water seals where a shaft runner acts as a pump to create a ring of water around the shaft. Use only treated water to avoid shaft pitting.
- Stuffing box using woven or soft packing rings that are compressed with a gland to prevent leakage along the shaft.
Wednesday, January 1, 2020
How Is Oil Pressure Maintained When Starting Or Stopping A Medium-sized Turbine?
An
auxiliary pump is provided to maintain oil pressure. Some auxiliary
pumps are turned by a hand crank; others are motor-driven. This pump is
used when the integral pump is running too slowly to provide pressure,
as when starting or securing a medium-sized turbine.
How Is A Flyball Governor Used With A Hydraulic Control?
What Are Some Conditions That May Prevent A Turbine From Developing Full Power?
- The machine is overloaded.
- The initial steam pressure and temperature are not up to design conditions.
- The exhaust pressure is too high.
- The governor is set too low.
- The steam strainer is clogged.
- Turbine nozzles are clogged with deposits.
- Internal wear on nozzles and blades.
Subscribe to:
Posts (Atom)